Dak Mi 4 Hydropower Plant

Location icon Quang Nam, Provincia di Quang Nam, Vietnam, Vietnam
With 4000m length and 6.5m diameter, the headrace tunnel was excavated by New Austria Tunneling Method (NATM).
With total investment of VND4.547 billion (US$226 million), the project provides more than 780 million kWh of electricity per year.
Ref #: 0
Category:

Construction

Location Quang Nam, Provincia di Quang Nam, Vietnam, Vietnam
Subcategory
Built in 2007
Opened in 2010
Application Type
Client Song Da Enterprise 10.1
Contractor company Song Da Enterprise 10.1

Product used for the project

EXPANFLUID
EXPANFLUID
Expansive anti-shrinkage agent for slurries for injection.
MAPEQUICK AFK 888
MAPEQUICK AFK 888
Alkali-free accelerator for shotcrete Where to use • Securing surfaces during…
692 - DYNAMON EASY 11
DYNAMON EASY 11
Product not available for this market,
contact us