Downtown Line Stage 2 - Contract 917
King Albert Park Singapore, Singapore
The S$320.7 million contract 917 is for the Design and Construction of Sixth Avenue and King Albert Park stations and tunnels.
Technical info: TBM type: 1x EPBM (Herrenknecht) with diameter 6.5m; tunnel length:2x 1200 m
MAPECOAT W SP, used for the concrete segment protection proved to be resistant to the abrasion caused by the passage of the TBm tail brushes and confirmed to be leader in its sector.
Construction
|
|
Location |
King Albert Park Singapore, Singapore
|
Subcategory |
|
Built in |
2011
|
Opened in |
2014
|
Application Type |
|
Client |
LTA
|
Contractor company |
Alpine GMBH; McConnell Dowell SE Asia (Australia)
|
Browse the project Gallery