Two TBM - EPB manufactured by Herrenknecht are currently excavating the Metro Line 5 that constitutes phase IV of the Bucharest metro modernization project. The Section 2 of the line n.5 will be 8.7 km-long. Two parallel tunnels each of 5.7 m-diameter and 4.85 km-long are under construction.
Ref #: 0
Category:
Construction
Location
Bucharest, Romania, Romania
Subcategory
Application Type
Client
Metrorex
Contractor company
Astaldi (Italy) - Fomento de Construcciones y Contratas (Spain) - AB Construct (Romania)
Liquid activator admixture used in extremely fluid backfill grouts systems, even with thigh water content, to be used in mechanized tunnelling with TBM
Liquid activator admixture used in extremely fluid backfill grouts systems,…
High performance liquid foaming agent, based on biodegradable anionic surfactants, in combination with a natural lubricating polymer, for ground conditioning in mechanized tunneling
High performance liquid foaming agent, based on biodegradable anionic…
One-component, ultra-fluid polyurethane resin applied by injection for waterproofing structures and ground and rocks subject to intense percolating water. The reaction time may be regulated.
One-component, ultra-fluid polyurethane resin applied by injection for…