U12-1 Heilbronner Straße
Stuttgart, Germania, Germany
The project is a follow up to the project Stuttgart 21. The construction project include 2 underground tunnel with a length of 600m and 2 underground tunnel with a length of 250m
The tunnels was excavated by traditional drill and blast method with shotcrete application: MAPEQUICK 043 FFG (SBE) was the shotcrete accelerator used for the project.
Construction
|
|
Location |
Stuttgart, Germania, Germany
|
Subcategory |
|
Built in |
2013
|
Opened in |
2014
|
Application Type |
|
Client |
Stuttgarter Straßenbahn AG
|
Contractor company |
Ed. Züblin AG
|