U12-1 Heilbronner Straße
                        
                            
                                 Stuttgart, Germania, Germany
                                
                                    Stuttgart, Germania, Germany
                                
                             
                            
                                The project is a follow up to the project Stuttgart 21. The construction project include 2 underground tunnel with a length of 600m and 2 underground tunnel with a length of 250m
The tunnels was excavated by traditional drill and blast method with shotcrete application: MAPEQUICK 043 FFG (SBE) was the shotcrete accelerator used for the project.
                            
                        
                        Construction
                        
    
        
            
                |  |  | 
        
        
            
                
                    | Location | Stuttgart, Germania, Germany | 
            
                | Subcategory |  | 
                
                    | Built in | 2013 | 
                
                    | Opened in | 2014 | 
            
                
                    | Application Type |  | 
                
                    | Client | Stuttgarter Straßenbahn AG | 
                
                    | Contractor company | Ed. Züblin AG |